Voneus Superfast Broadband – Update

Alan Seldon of Voneus is now managing the Kingscote project and will update us regularly on progress.

To date, the situation is:

The A Side fibre backhaul will be coming from the village of Amberley. The two original sites identified are no longer viable due to permission being withdrawn. Voneus has now identified another suitable site and has an appointment this Friday to meet with the owners, show them the equipment and hopefully gain their permission to install it.

Two main sites needed as hop points have been identified; one has agreed and an installation date is imminent; the other has been sent the outline statement of works and a response to agreement/installation is awaited.  Once these points are installed, two “hop points” need to be identified within the village.  A test signal will then be sent out to potential hop points to test their viability.

This means there will be an installation delay due to both the permissions being withdrawn, and the fact that BT has not yet installed the fibre requested.

Bagpath will be treated as a separate project but work on it will begin before the Kingscote project is completed.

Alan Seldon is happy to answer questions at any time.  Details below:

Alan Seldon
Broadband Customer Operations Director
+44 (0)20 3026 4103   +44 (0)788 418 7446
Voneus Limited | Southgate Office Village
1st Floor – Block B | 284A Chase Road | London N14 6HF
@voneusbroadband   www.voneus.comHelpdesk +44 (0)20 3026 4111 | Sales +44 (0)20 3026 4123